Roof Project week 2

On January 21, 2013, in Claremont, by John Enger
The weekend update: Heat will be off or limited in the Living room, the North Hall and a portion of the Great Hall starting Monday. Please plan accordingly.

Clubhouse Roof Project

On January 16, 2013, in Claremont, by John Enger
The Clubhouse roof project is in full swing. Next week we anticipate work to begin on the flat roof section over the Living Room which means that we may be without heat in sections of the Clubhouse.

WHAT??!!?? NO GARBAGE DISPOSAL??

On March 16, 2012, in Claremont, by John Enger
Yes, yes, we know. When we were soliciting resident input for the kitchen renovation, one of the top requests was for a garbage disposal at the main sink. And now it is the top question we are receiving about the renovation. It sounded like a reasonable request at the time—however—when we talked with caterers that […]

Update on the Claremont Clubhouse Kitchen Renovation Project

On March 2, 2012, in Claremont, by John Enger
At the February 16 regular board meeting, the CCA Board approved the final plans and budget for the kitchen renovation. The approved plan calls for construction to begin in the kitchen next week. Volunteers are already packing up kitchen supplies and equipment so that the kitchen is totally vacant before work begins. The first phase […]